Beasley Creek – Flamingo Interpreted as Copper/ Gold VMS System
with Orogenic Gold Overprint
HIGHLIGHTS
➢ Flamingo reinterpreted as a compelling Cu–Au VMS-style target, materially upgrading
Beasley Creek from a single-model gold project to a multi-commodity volcanic–
hydrothermal opportunity
➢ Builds on Catalina’s confirmed VMS system at Breakaway Dam, positioning the
Company with growing copper leverage
➢ Large 600m x 400m magnetic feature with coherent Au–Cu–Zn–Ni–As anomalism,
defining a structurally controlled corridor consistent with VMS-style mineral systems
➢ Gold upside remains intact, with evidence supporting later orogenic remobilisation
capable of enhancing and upgrading earlier mineralisation
➢ First modern drill test pending, with RC program designed to validate the VMS–orogenic
hybrid model; EIS co-funding application in development to accelerate drilling and
maximise capital efficiency
Catalina Resources Limited (“Catalina” or “the Company”) is pleased to provide an update to its previous
Beasley Creek announcements following completion of further geological review and integrated
reinterpretation of structural, geochemical and geophysical datasets.
Ongoing technical work has materially strengthened the exploration thesis at the Flamingo target. The
Company now interprets Flamingo as demonstrating the characteristics of a dismembered Archean
copper-dominant Volcanogenic Massive Sulphide (VMS) system with associated gold, subsequently
overprinted by orogenesis and remobilisation of gold.
This refined geological model materially expands the project’s commodity exposure beyond gold alone and
increases the potential scale of the opportunity, positioning Flamingo as a prospective Cu–Au volcanic-
hydrothermal system rather than a single-model gold target.
Catalina Executive Director, Ross Cotton, commented:
“The refinement of the Flamingo model is a material step forward for Beasley Creek and reinforces the
purposeful direction Catalina has taken with its portfolio. We already have a confirmed VMS system at
Breakaway Dam, and recognising VMS-style characteristics at Flamingo strengthens our conviction that the
Company is building meaningful exposure to copper through technically grounded opportunities.
VMS systems are attractive for their potential scale, metal zonation and repeatability within defined volcanic
corridors. The coherent magnetic architecture, multi-element geochemical support and structural setting at
Flamingo provide a compelling basis to advance drilling with confidence.
ASX Announcement
25 February 2026
Page 2
Importantly, this is not a single-commodity story. While the VMS interpretation introduces clear copper
potential, the orogenic overprint and regional setting mean the gold upside remains intact. If validated
through drilling, Flamingo has the potential to materially enhance both the copper and gold opportunity
within Catalina’s portfolio.”
REGIONAL CONTEXT AND BACKGROUND
Catalina’s 100% owned Beasley Creek Project lies within a broader district (Figure 1 and 2) that hosts
several established gold deposits, including the former Paulsens Gold Operation. Paulsens produced
907,344 oz at 7.3 g/t Au, averaging approximately 75koz per annum between 2005 and 20171
. The operation
was subsequently acquired by Black Cat Syndicate (ASX:BC8) for remnant mining of the existing resource,
with first gold poured in December 2024.
Figure 1. Regional location diagram of the Beasley Gold Project (E47/3490)
Beasley Creek occupies a geologically prospective and underexplored portion of this district, where
historical work has been limited in scope and depth, with minimal modern geophysics or systematic
geochemical testing undertaken to date.
Exploration to date focused almost exclusively on conglomerate gold, with drilling confined to the basal
conglomerate and immediately adjacent shear quartz zones just south of the conglomerate. Flamingo
(~700 m south of the conglomerate) was not previously considered a bedrock source. New datasets
including aerial photo mapping, soil geochemistry, rock chips, and airborne geophysics define a
hydrothermal system unrelated to the conglomerate.
Soil anomalies (200 × 40 m spacing), within the Flamingo target, show elevated Au, Cu, Zn, Ni and As
values. These multielement patterns align with known VMS halos. Iron rich units < 40 m north of Flamingo
are interpreted to represent an early sea-bed smoker system rather than sedimentary ironstone. Visible
nuggets are best explained by downslope transport from a Cu–Au bedrock source at Flamingo.
Page 3
Figure 2. Beasley Creek Regional Geology including the Beasley Creek project and additional tenements (pending)
KEY ELEMENTS OF THE REFINED GEOLOGICAL INTERPRETATION
Primary VMS System
The Flamingo target area (figure 3) is interpreted to represent the structurally modified remnants of an
Archean VMS system.
Key supporting observations include:
➢ A 600m x 400m magnetic high exhibiting internal repetition indicate fault segmented lithology (figure
4)
➢ Multi-element soil anomalies (Au–Cu–Zn–Ni–As) consistent with VMS halo signatures (figures 5 – 9)
➢ Iron rich units, interpreted from arial photomapping and rock chip sampling, along with Cu
anomalies, suggest an early sea-bed smoker complex.
➢ North-dipping bedding bounded by NW–SE faults within the Mithgoondy Shear Zone
The original Archean VMS geometry appears to have been strongly modified by Proterozoic deformation,
with tilting, folding and shearing dismembering the system into structurally rotated blocks.
Page 4
Figure 3. 100k Geology and historic drilling and target areas including Flamingo
Figure 4. Airborne Magnetics TMI and structures
Page 5
Figure 5. Historical Au ppb soil samples
Figure 6. Historical Cu ppm soil samples
Page 6
Figure 7. Historical Zn ppm soil samples
Figure 8. Historical Ni ppm soil samples
Page 7
Figure 9. Historical As ppm soil samples
Orogenic Gold Overprint
A 2018 GSWA SEM-EDS and LA-ICP-MS study of gold nuggets (Figures 10 and 11) from the broader Beasley
River area concluded that the gold is hydrothermal in origin, proximal to source, characterised by elevated
silver content, and only minimally modified by burial processes. These characteristics indicate limited
transport distances and support derivation from a nearby bedrock source.
This interpretation is consistent with the regional geological setting as the Beasley Creek Project lies within
the northern Capricorn Orogen, a terrane characterised by repeated orogenesis and reactivation of mantle
tapping structures creating fluid pathways. Major crustal-scale structures within this framework provide a
credible mechanism for remobilisation and local upgrading of earlier VMS-related mineralisation,
supporting a hybrid Cu–Au system model at Flamingo.
Page 8
Figure 10. Gold nugget from Beasley Creek, with angular character, from GSWA, mineral report on sample 210968
Figure 11. Reflected light of etched polished section of gold nugget, showing internal crystalline structure, from GSWA, mineral
report on sample 201968
Significance of the Updated Model
The refined geological interpretation expands the conceptual exploration framework across the Beasley
Creek Project and surrounding tenements held by the Company in the district.
The focus shifts from conglomerate-hosted gold toward evaluation of a structurally controlled volcanic–
hydrothermal corridor interpreted to exhibit characteristics consistent with a Cu–Au VMS-style system, with
potential later gold remobilisation.
The reinterpretation:
➢ Introduces copper as a potential additional commodity within the system, broadening the
exploration focus beyond gold
Page 9
➢ Supports evaluation of a hybrid mineralisation model involving primary volcanic-hosted
mineralisation and possible subsequent orogenic remobilisation
➢ Establishes a structural and geochemical framework that may be applicable to other prospective
areas within Catalina’s broader Beasley Creek landholding
Importantly, the Flamingo volcanic–hydrothermal corridor has not been directly tested by drilling. The 48
RC holes completed in 1994 were confined to the basal conglomerate and adjacent shear zones and did
not test the interpreted target area. No modern drilling has been undertaken in this corridor.
Further drilling is required to test the conceptual model and determine whether mineralisation consistent
with this interpretation is present.
Implications for Forward Exploration
The Company’s has designed an RC drilling program to test:
➢ Predicted VMS footwall positions
➢ Gossanous horizons at unconformity contacts
➢ Alteration zones indicated by geochemistry and magnetics
➢ Structural offsets within north-dipping blocks
Drilling will allow the Company to distinguish between:
➢ Primary VMS mineralisation
➢ Orogenic remobilisation
➢ Or a hybrid system involving both processes
If validated, the Flamingo target may represent a previously unrecognised Cu–Au volcanic-hydrothermal
corridor within the Rocklea Dome.
2026 Exploration Incentive Scheme (EIS) Co-Funding Application
As previously announced2
Catalina will be applying for co-funding under the current round of the Western
Australian Government’s Exploration Incentive Scheme (EIS) to support the initial drilling program at
Beasley Creek.
Securing co-funding would enable Catalina to accelerate first-pass and confirmatory drilling activities while
applying capital more efficiently across the broader portfolio.
Next Steps
➢ Complete soil infill and extension sampling across the Flamingo Target and other identified
locations that represent a similar signature to refine drill collar locations and finalise target
footprints.
➢ Conduct geological field mapping within the Flamingo target area and other priority areas.
➢ Finalise heritage engagement, access planning and operational logistics required in advance of
exploration activity.
➢ Commence drilling activities—including the RRC15 confirmation hole and first-pass drilling along
the Flamingo structural corridor.
Catalina will provide further updates as each stage of the work program is advanced and finalised.
Page 10
Contacts
Investors/ Shareholders
Ross Cotton
Executive Director
T: +61 (0)8 6165 8858
References (ASX)
This Report contains information extracted from ASX market announcements reported in accordance with
the 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves” (“2012 JORC Code”). Further details (including 2012 JORC Code reporting tables where
applicable) of exploration results referred to in this announcement can be found in the following
announcements lodged on the ASX:
1
BC8 ASX Announcement 28 March 2023: Paulsens Corridor Exploration Update - Cu-Ag-Au Potential
2
CTN ASX Announcement 8 December 2026: Independent-Review-Confirms-Gold-Potential-at-Beasley-
Creek.pdf
The Company confirms that it is not aware of any new information or data that materially affects the
information in the original reports, and that the form and context in which the Competent Person’s findings
are presented have not been materially modified from the original reports.
Competent Person Statement
The information in this announcement that relates to exploration activities within the Beasley River Project
is based on information compiled by Dr Nishka Piechocka, PhD, Vice President of the Australian Institute of
Geoscientists (AIG) and a full-time employee of Catalina Resources Ltd. Dr Piechocka has sufficient
experience relevant to the style of mineralisation and type of deposit under consideration and to the activity
being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code
for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code). Dr Piechocka
consents to the inclusion in the report of the matters based on her information in the form and context in
which it appears.
Where the Company refers to the Mineral Resources in this report (referencing previous releases made to
the ASX), it confirms that it is not aware of any new information or data that materially affects the
information included in that announcement and all material assumptions and technical parameters
underpinning the Mineral Resource estimate with that announcement continue to apply and have not
materially changed.
Forward-Looking Statements
This announcement contains forward-looking statements that are subject to a range of risks and
uncertainties. These statements relate to the Company’s expectations, intentions, or strategies regarding
the future. These statements can be identified by the use of words like “anticipate”, “believe”, “intend”,
“estimate”, “expect”, “may”, “plan”, “project”, “will”, “should”, “seek” and similar words or expressions
containing same. These forward-looking statements reflect the Company’s views and assumptions with
respect to future events as of the date of this release and are subject to a variety of unpredictable risks,
uncertainties, and other unknowns. Actual and future results and trends could differ materially from those
Page 11
set forth in such statements due to various factors, many of which are beyond our ability to control or
predict. These include, but are not limited to, risks or uncertainties associated with the acquisition and
divestment of projects (including risks associated with completing due diligence and, if favourable results
are obtained, proceeding with the acquisition of the Beasley Creek Project), joint venture and other
contractual risks, metal prices, exploration, development and operating risks, competition, production
risks, sovereign risks, regulatory risks including environmental regulation and liability and potential title
disputes, availability and terms of capital and general economic and business conditions.
Given these uncertainties, no one should place undue reliance on any forward-looking statements
attributable to the Company, or any of its affiliates or persons acting on its behalf. Subject to any continuing
obligations under applicable law the Company disclaims any obligation or undertaking to disseminate any
updates or revisions to any forward-looking statements in this announcement to reflect any change in
expectations in relation to any forward-looking statements or any change in events, conditions or
circumstances on which any such statement is based.
ABOUT CATALINA RESOURCES LIMITED
Catalina Resources Limited is an Australian diversified mineral exploration and mine development
company whose vision is to create shareholder value through the successful exploration of prospective
gold, base metal, lithium and iron ore projects and the development of these projects into production.
Page 12
Beasley River Project
APPENDIX 1: JORC CODE, 2012 EDITION - TABLE 1
JORC Code, 2012 Edition – Table 1 report template
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard measurement
tools appropriate to the minerals under
investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc).
These examples should not be taken as
limiting the broad meaning of sampling.
• Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any measurement
tools or systems used.
• Aspects of the determination of
mineralization that are Material to the Public
Report.
• In cases where ‘industry standard’ work has
been done this would be relatively simple (eg
‘reverse circulation drilling was used to obtain
1 m samples from which 3 kg was pulverised
to produce a 30 g charge for fire assay’). In
other cases more explanation may be
required, such as where there is coarse gold
that has inherent sampling problems.
Unusual commodities or mineralization types
(eg submarine nodules) may warrant
disclosure of detailed information.
• Exploration activities on the Beasley project
have been completed by CRA, Vageta Pty Ltd,
and Castle Minerals between 1993 and 2022.
CRA completed initial stream sediment
sampling in 1993 (primarily targeting Nickel),
Vageta Pty Ltd completed RC drilling in
1998/1999 targeting gold, and between 2017
and 2022 Castle Minerals Ltd completed
several stream sediment and soil sampling
programs targeting gold.
• CRA stream sediment samples were
collected from active stream channels.
Samples were sieved in field and 150-250
grams of minus 80 mesh material was
retained for analysis.
• Vegata Pty Ltd conducted Reverse Circulation
(RC) drilling. Sampling was carried out using
protocols established by Vageta Pty Ltd at the
time. RC samples were described as being
collected as single metre intervals. No other
details are available. The gold mineralisation
expected in the conglomerate unit is coarse
grained with a high nugget component
causing sampling to be problematic. No
description of the methods used to undertake
the sampling have been described. It is
assumed standard industry techniques were
applied. Four metre composite samples were
routinely collected down the hole and
submitted for assay.
• Castle Minerals Ltd collected stream
sediment samples from streams draining
areas downstream from prospective
conglomerate beds. Stream sediment
samples were collected from the base of the
stream bed by digging. Sample material was
Page 13
Criteria JORC Code explanation Commentary
sieved to - 2mm to remove coarser material.
Approximately 15kg of sieved material was
collected at each trap site for processing. The
stream sediment sample technique collects
material from a large area drained by the
creek. The technique is used widely in the
exploration industry as a first pass tool to
access areas for anomalous metal
concentrations that can be tracked up stream
to their source. The stream sediment sample
collection method is industry standard. The
samples were processed using a portable wet
sluice to produce a concentrate. This
concentrate was panned off to reveal
recovered gold. The company employed field
personnel with experience operating similar
equipment in order to ensure accurate results
were obtained. A subsample of the bulk
stream sediment sample was collected for
laboratory analysis.
Castle Minerals Ltd soil samples are
homogenised by the collection process. Soil
sampling results are a first pass exploration
technique that can assist in vectoring toward
mineralisation. Soil sampling is regarded as a
standard first pass exploration techniques.
For soil sampling, at the selected sample
site, a small hole is dug to a depth of
approximately 20 cm. The soil material at the
base of the hole was sieved, and
approximately 2kg of –2mm soil material was
collected into a numbered calico bag.
Drilling
techniques
• Drill type (eg core, reverse circulation, open-
hole hammer, rotary air blast, auger, Bangka,
sonic, etc) and details (eg core diametre,
triple or standard tube, depth of diamond
tails, face-sampling bit or other type, whether
core is oriented and if so, by what method,
etc).
• Reverse Circulation drill technique was used
by Vegata Pty Ltd
Drill
sample
recovery
• Method of recording and assessing core and
chip sample recoveries and results assessed.
• Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
• Whether a relationship exists between
sample recovery and grade and whether
sample bias may have occurred due to
preferential loss/gain of fine/coarse material.
• The gold mineralisation in the conglomerate
rocks is believed to be coarse grained with a
high nugget effect. The size of the sample and
method of processing the samples is critical
in establishing accurate grades for the
intersections. The small sample size
collected by RC drilling is not sufficient to
accurately estimate the grade of the
mineralisation.
Logging
• Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
• All drill holes were geologically logged. The
descriptions appear to be complete and
provide a geological framework to constrain
the mineralisation.
• Geological logging recorded a description of
Page 14
Criteria JORC Code explanation Commentary
• Whether logging is qualitative or quantitative
in nature. Core (or costean, channel, etc)
photography.
• The total length and percentage of the
relevant intersections logged.
the major lithologies recovered from the drill
chips. Quantitative estimates of the
percentage of quartz veining were made.
• All drill holes were geologically logged.
Sub-
sampling
techniques
and
sample
preparation
• If core, whether cut or sawn and whether
quarter, half or all core taken.
• If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or
dry.
• For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
• Quality control procedures adopted for all
sub-sampling stages to maximise
representivity of samples.
• Measures taken to ensure that the sampling is
representative of the in situ material
collected, including for instance results for
field duplicate/second-half sampling.
• Whether sample sizes are appropriate to the
grain size of the material being sampled.
• CRA stream sediment sample preparation
included riffling out enough material required
for assay and store remainder. Dry and fine
pulverise to minus 200 mesh in Cr free bowl
with quartz wash between samples.
• Vegata composite 4m samples were prepared
from the 1m samples collected during the
drilling. No details were provided on how the
composite samples were collected. For
sampling gold mineralisation with an
expected high component of coarse gold the
sample size is not considered representative.
The sample size is not considered sufficient
to adequately represent the mineralisation.
Castle subsample from the bulk stream
sediment sample was collected by PVC tube
sampling through the sieved and
homogenized bulk sample. The entire bulk
sample (stream sediment) was processed
through the field concentrator and panned
off. The concentration and panning was
undertaken by field personnel familiar with
the equipment or similar equipment.
Between each sample the concentrator and
pan dish was thoroughly cleaned The entire
subsample was bottle roll leached in a
solution of cyanide to dissolve any gold in the
sample. The liquor was analysed for gold by
atomic absorption technique (AAS). No
specific quality control measures were
adopted for the subsampling of the bulk
stream sediment samples. The process was
undertaken by experienced personnel in the
field. No field duplicates were collected
during stream sediment sampling. Due to the
coarse nature of the gold, sample size is
important to obtain a representative sample
of the material to be tested. No work has
been undertaken on the appropriate sample
size however 15kg samples are being
collected by other companies undertaking
similar exploration in the area.
Page 15
Criteria JORC Code explanation Commentary
Castle soil samples were sieved to collect
the -2 mm fraction. All samples were dry. The
entire sample was pulverized to a nominal -
80 micron at the laboratory. Once the
sample was pulverized a 25 gm subsample
was taken by a scoop for digestion. There
was no subsampling. Field repeat soil
samples were collected every 50th sample.
The sample size is considered appropriate
for the material being sampled.
Quality of
assay data
and
laboratory
tests
• The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
• For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the analysis
including instrument make and model,
reading times, calibrations factors applied
and their derivation, etc.
• Nature of quality control procedures adopted
(eg standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (ie lack of bias) and
precision have been established.
• CRA samples were submitted to Analabs in a
single batch. Gold was analysed by fire assay
using a 50 g charge with a detection limit of
0.001 pmb. Platinum and palladium were
determined by ICP-MS following lead
collection, with detection limits of 0.5 ppb.
Other elements were analysed using partial
acid digestion (HClO₄, HCl, HNO₃) and
Atomic Absorption Spectroscopy (AAS) for
major and trace metals, including: Mg (HF,
HClO₄, HNO₃, HCl digestion; AAS; detection
limit 100 ppm), Fe (HClO₄, HCl, HNO₃
digestion; AAS; detection limit 5 ppm), Ag (1
ppm), Co (3 ppm), Cr (7 ppm), Cu (2 ppm), Mn
(3 ppm), Ni (5 ppm), Pb (3 ppm), Zn (2 ppm).
Eight samples were duplicated in field and
secreted into the analytical batch.
• Vegata RC samples were submitted to ALS
Laboratories Pty Ltd. Gold was analysed by
the PM205 technique with a lower detection
limit of 0.001 ppm. Cu, Pb, Zn, Ag, As, Fe, Bi,
Cd, Co, Mg, Mn, Mo, Ni, P, Sb, Cr were
analysed by the IC 205 technique. Only
internal laboratory QA/QC was undertaken for
RC drilling and stream sediment sampling
programs.
• The Castle stream sampling program utilised
a two stage process. The presence or
absence of visual gold was determine using
the field concentrator and panning technique.
Cyanide leachable gold was determined
using the bottle roll technique. Both
techniques are considered suitable for the
style of mineralisation being explored. Both
techniques are considered partial. No
geophysical surveys undertaken. No external
duplicates or blanks were submitted.
Standard internal laboratory checks were in
place.
Castle 25g sub sample of the soils were
digested in an aqua regia solution and
analysed for a multielement suite by ICP OES
Page 16
Criteria JORC Code explanation Commentary
or MS. The aqua regia technique is not a
complete digestion but for soil material is
considered adequate. A 30g subsample of
form the pulverized rock chip sample was
fire assayed and analysed for Au, Pt, Pd.
Another subsample was digested in a 4 acid
solution and analysed for a multielement
and REE . The 4 acid digestion is considered
a total digestion. Field repeat sample was
collected every 50th sample and given a
separate sample number. These samples
were collected in an identical manner to the
original sample.
Verification
of sampling
and
assaying
• The verification of significant intersections by
either independent or alternative company
personnel.
• The use of twinned holes.
• Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
• Discuss any adjustment to assay data.
• There is no documentation of the verification
of anomalous Au intercepts by CRA.
• There is no documentation of the verification
of anomalous intercepts by Vegeta Pty Ltd
however during the 2018 Castle field
campaign, the remnants of sample bags from
several holes were located close to drill
collars. The bags were in a highly degraded
condition and depth intervals obscured.
Metal detecting of the sample bags failed to
identify any gold nuggets or flakes.
• Castle stream sediment sampling was
considered early stage exploration and the
type of work completed to date, no
independent verification or assaying has been
undertaken.
As part of the Castle soil program anomalous
geochemical thresholds were determined by
a senior geologist. Pre-numbered sample
bags were used. Field operators were
provided with an electronic file of the
planned sample locations to load into a GPS.
The actual sample location was recorded as
a waypoint with the sample number of the
sample collected. The operator provided a
digital copy of the downloaded GPS file. No
adjustments to assay data were undertaken.
Location of
data points
• Accuracy and quality of surveys used to
locate drill holes (collar and down-hole
surveys), trenches, mine workings and other
locations used in Mineral Resource
estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• CRA stream sediment sample locations were
determined with GPS instruments and
marked on air photographs for back up in
cases where poor satellite configuration
caused wildly erroneous readings.
• Vegata initially recorded coordinates for the
drill holes in local grid coordinates. During the
Castle field mapping campaign, the
Page 17
Criteria JORC Code explanation Commentary
coordinates of the drill holes were measured
by hand held GPS with an accuracy of
approximately 3m. The hole identifications
were made by comparing drill plans in the
report with the GPS drill pickup.
Local grid and GDA 94 Zone 50 datum. The
topography in the area of drilling has
moderate relief, the accuracy of the
elevation data from a GPS may only be
accurate to +/-10m, and is not considered to
be an absolute elevation reading.
• Castle stream sediment sample locations
were recorded from a hand-held GPS.
Accuracy is approximately +/- 2m, and
locations compared with recent colour aerial
photography. GDA94 zone 50 projection. The
combination of aerial photography and GPS
readings are considered sufficiently accurate
for the stage of exploration.
During the Castle soils programs the
operator used a GPS unit to navigate to each
predetermined soil sample site. The actual
sample site was recorded as a way point.
GDA 94, zone 50. GPS measurements of soil
sample positions are sufficiently accurate for
first pass geochemical sampling.
Data
spacing
and
distribution
• Data spacing for reporting of Exploration
Results.
• Whether the data spacing and distribution is
sufficient to establish the degree of geological
and grade continuity appropriate for the
Mineral Resource and Ore Reserve estimation
procedure(s) and classifications applied.
• Whether sample