CATALINA FAST-TRACKS BADJA PROJECT
SCOPING STUDY AND FIELDWORK UNDERWAY
Highlights
➢ Badja ScopingStudy advances, Minecompengaged torecommence the firsteconomic
assessment of the Project
➢ Badja’s current Mineral Resource Estimate (MRE) is 90,358oz Au (1.11Mt at 2.52 g/t
Au), including 82,208oz Au Indicated (JORC 2012)
➢ Fieldwork to commence shortly with surveying and pegging of drill pads at Gnows Nest
ahead of earthworks.
➢ All Programs of Work (POW) are approved
➢ Drilling scheduled to commence in January 2027, targeting extensions of the high-
grade Gnows Nest lode below the historical workings, where previous drilling returned¹:
o 13m @ 13.73 g/t Au from 39m, including 2m @ 76.24 g/t Au from 43m
(18GNRC048);
o 3m @ 42.18 g/t Au from 77m, including 2m @ 61.11 g/t Au from 78m
(21GNRC138); and
o 2m @ 11.43 g/t Au from 208m, including 1m @ 15.68 g/t Au from 208m
(21GNRC232).
➢ Scoping Study and drilling to run in parallel, with drilling results to feed directly into the
study’s mine design.
Catalina Resources Limited (ASX: CTN) (Catalina or the Company) is pleased to announce
that it has engaged Minecomp Pty Ltd (Minecomp) to recommence the Scoping Study on the
Badja Gold Project (Badja or the Project) in Western Australia's Mid-West. This fieldwork is
scheduled to commence ahead of the Company’s maiden drilling program at the Project.
The two workstreams follow the Company’s announcement of the Badja Project acquisition on
10 November 2026¹. This work reflects Catalina's focus on advancing the Project quickly on
two fronts: growing the high-grade resource at Gnows Nest and assessing the Project's
economics.
Managing Director, Jade Smith, commented:
“We told the market we would move quickly at Badja, and we are. Within days of announcing
the acquisition, the Scoping Study is back underway, our team is on the ground and we are
cleared to drill.
19 NOVEMBER 2026
ASX Announcement
Page 2
Minecomp knows Badja well, so we are not starting from scratch. Engaging them lets us build
on work already done and get to results sooner.
Gnows Nest was mined at more than 20 grams per tonne, and drilling has shown that the lode
continues below the old workings. Its high-grade core is where Minecomp’s work starts, and
our January program is designed to test its extensions at depth. Every metre we drill will feed
straight into the study, and shareholders can expect steady news flow from here. We’re also
expecting upside in the poorly drilled ‘low grade’ zone, which will materially benefit project
economics with only modest upside”
Figure 1 – Badja Gold Project location relative to regional gold processing infrastructure and nearby projects
SCOPING STUDY – BUILDING ON EXISTING WORK
Minecomp was previously engaged on the Badja Gold Project and completed preliminary
mining assessment work, including open pit and underground optimisation. Catalina has
engaged Minecomp to recommence the Scoping Study from that existing work, allowing the
study to progress efficiently.
The Scoping Study will build on the Project’s JORC 2012 MRE of 90,358oz Au (1.11Mt at 2.52
g/t Au) , of which 82,208oz Au is classified as Indicated¹. The study’s initial focus is the Gnows
Nest deposit, which hosts an Indicated MRE of 59,551oz Au (428,762t at 4.32 g/t Au) ¹. As
previously reported, the high-grade core of the Gnows Nest Mineral Resource, being the
Page 3
portion above a 1 g/t Au cut-off, grades 7.13 g/t Au (0.25Mt)¹. The study will also assess the
Monte Cristo deposit, which hosts an Indicated MRE of 22,657oz Au (492,805t at 1.43 g/t Au)¹.
The study will assess:
➢ open pit and underground mining options, with an initial focus on the Gnows Nest and
Monte Cristo deposits;
➢ processing pathways, including toll treatment and ore sale options at regional
processing facilities within trucking distance of the Project;
➢ preliminary mine design, scheduling, and capital and operating cost estimates; and
➢ infrastructure, approvals and environmental requirements to support development.
The Scoping Study is expected to be completed in Q2 2027.
FIELDWORK UNDERWAY – CLEARED TO DRILL
Catalina’s field team will deploy to site in the week beginning 23 November 2026 to survey and
peg drill pads and access tracks at Gnows Nest. This work will define pad locations ahead of
earthworks, which are scheduled in December 2026.
All Programs of Work required for the planned drilling have been approved by the Department
of Mines, Petroleum and Exploration, and the Project is cleared to drill.
JANUARY 2027 DRILLING PROGRAM – TARGETING HIGH GRADE EXTENSIONS AT GNOWS
NEST
Drilling is scheduled to commence in January 2027. The program of approximately 17 RC and
diamond holes for 4,365m is designed to:
➢ Test extensions of the high-grade Gnows Nest lode below the historical workings,
where the lode remains open at depth;
➢ Test strike extensions beyond the current MRE;
➢ Infill areas most relevant to the Scoping Study's mine design; and
➢ Provide fresh material for metallurgical testwork and oriented diamond core for
geotechnical assessment.
Gnows Nest produced 27,925oz of gold at a recovered grade of 21.85 g/t Au between 1923 and
1941¹. Drilling by previous explorers intersected high-grade mineralisation beneath the
historical workings, highlighting the potential for extensions at depth.
Exploration Target
The January program is the first phase of an aggressive campaign to test the Gnows Nest and
Monte Cristo Exploration Target of ~0.8–1.7Mt @ 4.4–5.7 g/t Au for approximately 109,000–
303,000oz of contained gold¹. Initial drilling prioritises the Gnows Nest depth and strike
extensions, which make up the largest share of the Exploration Target, with the Monte Cristo
depth extensions to be tested in subsequent phases.
Page 4
The potential quantity and grade of the Exploration Target is conceptual in nature, there has
been insufficient exploration to estimate a Mineral Resource and it is uncertain if further
exploration will result in the estimation of a Mineral Resource. The Exploration Target is
separate from, and additional to, the existing Mineral Resources, and does not constitute a
Mineral Resource or Ore Reserve.
PROJECT BACKGROUND
Badja Gold Project – Overview
Badja lies in the Yalgoo Mineral Field of Western Australia's Mid-West, approximately 110km
south-west of Mount Magnet and within 100km of multiple gold processing plants. Access is
via the Great Northern Highway and the Geraldton–Mount Magnet Road.
The Project covers approximately 39km² across two granted Mining Leases, one Mining Lease
application and three Exploration Licences. It hosts four gold deposits – Gnows Nest, Monte
Cristo, Flying Emu and Water Tank – together with several additional exploration prospects.
Figure 2 – Badja Gold Project tenements, Mineral Resource deposits, prospects and historical drilling
Page 5
Mineral Resource Estimate (MRE)
Badja hosts a combined Indicated and Inferred JORC 2012 MRE of 90,358oz Au (1.11Mt at 2.52
g/t Au) across four deposits. The Project includes the historically mined Gnows Nest deposit,
where high-grade mineralisation remains open along strike and at depth, together with the
Monte Cristo, Flying Emu and Water Tank deposits.
Table 1: Badja Gold Project – Mineral Resource Estimate1
Deposit Classification Tonnes Au grade Ounces
Gnows Nest Indicated 428,762 4.32 59,551*
Monte Cristo Indicated 492,805 1.43 22,657 *
Flying Emu Inferred 115,729 1.75 6,500**
Water Tank Inferred 77,378 0.66 1,650**
Badja Total
Indicated +
Inferred
1,114,674 2.52 90,358
Mineral Resources are reported in accordance with the JORC Code (2012).
Gnows Nest and Monte Cristo are reported using a nominal 0.2 g/t Au cut-off grade applied during modelling.
Flying Emu and Water Tank are reported using a 0.5 g/t Au cut-off grade.
Gnows Nest – High-Grade Historic Mine and First Drilling Priority
Gnows Nest is an historic underground gold mine and the first target for Catalina’s drilling. The
deposit sits on granted tenure, including granted Mining Lease M59/739 at the centre of the
deposit and Exploration Licence E59/2315, with Mining Lease application M59/798 lodged over
the broader deposit area. The mine produced approximately 27,925oz of gold at an average
recovered grade of 21.85 g/t Au¹, and drilling by previous explorers has since returned high-
grade gold both within and below the old workings.
Standout historical drill intersections at Gnows Nest include¹:
➢ 13m @ 13.73 g/t Au from 39m, including 2m @ 76.24 g/t Au from 43m (18GNRC048);
➢ 3m @ 42.18 g/t Au from 77m, including 2m @ 61.11 g/t Au from 78m (21GNRC138);
➢ 9m @ 11.67 g/t Au from 47m, including 5m @ 20.70 g/t Au from 47m (GNRC026);
➢ 7m @ 10.12 g/t Au from 131m, including 1m @ 40.38 g/t Au from 131m (22GNRC239);
and
➢ 2m @ 11.43 g/t Au from 208m, including 1m @ 15.68 g/t Au from 208m (21GNRC232).
Sampling inside the old underground workings has also returned very high grades, including
1.42m @ 88.89 g/t Au (GN_222_64)¹.
Page 6
Catalina’s drilling will test the lode along strike and at depth, and target gaps in the historical
drilling to better define the mineralised system. Diamond drilling will also provide oriented core
for geotechnical logging and testwork, supporting pit and underground design in the Scoping
Study.
Figure 3 – Gnows Nest plan view showing significant historical drill intercepts and the interpreted mineralised zone
Monte Cristo – Second Gold Deposit with Tungsten Upside
Monte Cristo is the Project’s second priority area. It lies on granted Mining Lease M59/785 and
hosts an Indicated gold Mineral Resource of 22,657oz Au¹. Historical drilling has returned
several strong gold intersections¹ including:
• 3m @ 13.35 g/t Au from 67m, including 1m @ 19.90 g/t Au from 68m (21MC001);
• 6m @ 6.51 g/t Au from 120m, including 1m @ 22.77 g/t Au from 121m (21MC011);
and
• 4m @ 9.74 g/t Au from 32m (4m composite sample) (21MC022).
Page 7
The deposit remains open along strike and at depth¹, giving scope to grow the resource with
further drilling. Tungsten has also been identified at Monte Cristo, a separate exploration
opportunity alongside Catalina's gold focus.
Figure 4 – Monte Cristo plan view showing significant historical gold and tungsten drill intercepts
Exploration Upside Across the Wider Project
Beyond Gnows Nest and Monte Cristo, Badja offers further exploration opportunities that
Catalina will assess as its programs progress. These include the Flying Emu and Water Tank
deposits (which host Inferred MRE’s of 6,500oz Au and 1,650oz Au respectively¹) and other
prospective areas within the tenement package.
The Project contains a number of known gold occurrences and mineralised structures. These
provide scopeboth toextend the existing deposits andtodiscovernew zones ofmineralisation.
Page 8
Figure 5 – Flying Emu plan view showing significant historical gold and tungsten drill intercepts
Figure 6– Water Tank plan view showing significant historical drill intercepts
Page 9
This announcement has been authorised for release by the Managing Director of Catalina
Resources Ltd.
Contacts
Mr Jade Smith
Managing Director
T: +61 (0) 8 6188 8181
Investor Enquiries
George Ventouras
George@corporatestorytime.com
T: +61 (0) 418 945 353
Click Here to leave a question about this announcement and to visit our Investor Hub
REFERENCES (ASX)
This Report contains information extracted from ASX market announcements reported in accordance
with the 2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves” (“2012 JORC Code”). Further details (including 2012 JORC Code reporting tables
where applicable) of exploration results referred to in this announcement can be found in the following
announcements lodged on the ASX:
1. CTN ASX announcement 10 November 2026 ASX:CTN - Catalina Acquires 90kOz Mid-West WA
Gold Project
FORWARD-LOOKING STATEMENTS
This announcement may contain forward-looking statements, including statements about planned
drilling and the development of the Company’s projects. These statements are based on the
Company’s current expectations and are subject to risks and uncertainties, many of which are outside
the Company’s control, and actual results may differ materially. The Company does not undertake to
update any forward-looking statement except as required by law.
Page 10
COMPETENT PERSONS
All exploration results, mineral resource estimates and exploration targets in this announcement were
previously reported on 10 November 2026.
The competent persons in that announcement were as follows:
• Dr Nishka Piechocka (Historic Exploration Results)
• Mr Ben Pollard (Exploration Targets and Mineral Resource estimates for Gnows Nest and Monte
Cristo)
• Mr Steve Le Brun (Mineral Resource estimates for Flying Emu and Water Tank)
COMPLIANCE STATEMENTS
The Company confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcement and, in the case of estimates of Mineral
Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the
estimates in the relevant market announcement continue to apply and have not materially changed.
The Company confirms that the form and context in which the Competent Person’s findings are
presented have not been materially modified from original market announcement.